ALI SALMAN ALOBIEDEEN

Maintenance Manager Cement Plant Maintenance & Reliability Leadership
Tafilah

Summary

Maintenance Leader experienced in cement manufacturing with a focus on kilns, cement mills, grinding and crushing equipment, and utility systems. Delivered significant cost reductions and enhanced equipment reliability through strategic restructuring of maintenance operations and improved technical staffing. Committed to driving organizational performance and operational efficiency within maintenance departments.

Overview

2
2
Languages
1
1
Certification
2027
2027
years of professional experience

Work History

Maintenance Manager

Rashadya Cement Plant
01.2017 - Current
  • I lead a team of 60 people responsible for maintaining kilns, cement mills, grinding and crushing equipment, and utility systems.
  • restructured the maintenance department to improve how work is organized and managed.
  • reduced maintenance costs by 5% by relying on existing technical staff and reducing dependence on contractors.
  • developed a protocol for working with third-party contractors to standardize their performance and control their scope of work. I
  • applied reverse engineering to [add the parts or equipment] and improved the reliability of critical equipment.
  • reduced equipment stoppages and extended the operating life of critical equipment [add the percentage reduction in stoppages].
  • led efforts to reduce fugitive dust [add the measures and results].
  • improved root cause analysis and strengthened inspection and preventive maintenance programs. I use Maximo to plan work orders and track maintenance performance .
  • led efforts to explore the best cost country (BCC) market for sourcing
  • Coordinated mechanical, electrical, and instrumentation repairs to restore plant equipment quickly and safely.
  • Reviewed work orders, prioritized breakdowns, and assigned tasks to maintenance technicians and contractors.
  • Monitored spare parts inventory and reordered critical components to support continuous plant operations.
  • Enforced lockout-tagout procedures and safety standards during maintenance activities across production areas.
  • Improved equipment reliability by implementing a preventive maintenance program and managing repair schedules.
  • Scheduled regular inspections of equipment and facilities to manage wear
  • Developed detailed maintenance budgets, effectively controlling expenses while ensuring optimal equipment performance.
  • Created and implemented maintenance program to optimize operational efficiency and reduce downtime.
  • Created and submitted detailed reports to highlight maintenance activities and equipment performance.

Mechanical Manager

Rashadyeh Cement Plant
2011 - 01.2016
  • I supervised the execution of work on two production lines, each with a capacity of 3,600 tons per day.
  • reduced maintenance costs by relying on the existing technical workforce and reducing dependence on contractors.
  • carried out re profiling of the cement mill girth gear and reversed it to extend its service life time and reduce down time
  • performed kiln skewing (alignment) work I managed full maintenance of the raw mill
  • Directed preventive maintenance programs for kiln, crusher, and conveyor equipment.
  • Diagnosed mechanical failures and restored rotating equipment performance.
  • Implemented reliability improvements to reduce recurring mechanical issues.
  • Developed innovative solutions to complex mechanical problems, improving overall system performance.
  • Established safety protocols for all team members, reducing workplace accidents and maintaining a safe work environment.
  • Conducted root cause analysis for recurring issues, resolving underlying problems and preventing future occurrences.

Site Engineer (Projects)

Tafilah
01.2001 - 08.2002
  • upgrade the clinker cooler ,install new bag filter replace the kiln shell ,full maintenanace of raw mill
  • Coordinated subcontractors and site crews to maintain smooth daily work progression.
  • Monitored material deliveries and site inventory to prevent delays and shortages.
  • Reviewed technical documents and highlighted design conflicts for timely resolution.
  • Documented site progress, issues, and corrective actions for engineering and project teams.
  • Enforced health and safety requirements to reduce risks during construction activities.
  • Communicated with consultants and contractors to resolve site queries efficiently.
  • Checked technical designs and drawings for adherence to standards.
  • Recorded daily events and activities in site diary to evaluate process and improve productivity.
  • Coordinated with subcontractors ensuring their work met project specifications as well as monitored their progress towards completion deadlines.
  • Delivered projects on time and within budget constraints by effectively managing resources, schedules, and risks.
  • Inspected site activities to verify compliance with drawings, specifications, and quality standards.

Mechanical Engineer

Rashadyeh Cement Plant
03.1999 - 2003
  • I joined the plant as a Mechanical Engineer in March 1999 and worked in this role until 2009. I reduced equipment stoppages through improved maintenance planning and execution after that section head for fabrication and Raw mill shop from 2003 to 2009
  • section head for cement mill and packing from 2009 to 2011

Education

Bachelor of Science - Mechanical Engineering

Mutah University
Jordan
01-1998

Skills

Department restructuring, maintenance cost control, reliability improvement, girth gear re profiling and reversal, kiln scewing , root cause analysis, inspection and preventive maintenance, fugitive dust control, third-party contractor management, shutdown management, maintenance KPI monitoring (MAXIMO), project management, Maximo, SAP (MMS), team leadership, soft skills

Department restructuring Maintenance cost control Reliability improvement Girth gear re profiling and reversal Kiln alignment Root cause analysis Inspection and preventive maintenance Fugitive dust control Third-party contractor management Best cost country (BCC) sourcing Shutdown management Project management Maximo SAP (MMS) Team leadership Soft skills

Accomplishments

  • Years in Cement Manufacturing: 27+
  • Team Members Led: 60
  • Capacity per Production Line: 3,600 tons/day
  • Maintenance Cost Reduction: 5%

Certification

MMDP Certificate: Foundation (ball mill maintenance, kiln maintenance, grinding, electrical power drives, gas handling and fans, instrumentation, lubrication and hydraulics, thermal and transport); Core HSE and People (HSE, people management, decision making, problem solving); Core Business and Specific (communication, finance , CIF basics, MMS and SAP, maintenance systems and processes, equipment reliability, performance management, project management, shutdown management).

Target Position

Maintenance Manager

Personal Information

  • Date of Birth: 1975-07-10
  • Nationality: Jordanian

Timeline

Maintenance Manager

Rashadya Cement Plant
01.2017 - Current

Site Engineer (Projects)

Tafilah
01.2001 - 08.2002

Mechanical Engineer

Rashadyeh Cement Plant
03.1999 - 2003

Bachelor of Science - Mechanical Engineering

Mutah University

Mechanical Manager

Rashadyeh Cement Plant
2011 - 01.2016
ALI SALMAN ALOBIEDEENMaintenance Manager Cement Plant Maintenance & Reliability Leadership